Job price and margin

Cost the job, set the margin, and see the price and the price per watt before and after certificates.

Rails, cable, isolators, switchgear
Lead cost, travel, admin
From the STC calculator
Price ex GST $11,800
Cost$8,850
Margin$2,950 (25% margin, 33.3% markup)
Per watt$0.89/W
STC value$2,964
After STCs$8,836
Per watt after STCs$0.67/W
Price inc GST, before STCs$12,980

How it's worked out

Price = cost ÷ (1 − margin). Margin is profit as a share of the price; markup is profit as a share of the cost, so a 25% margin is a 33% markup.

Your own costs. GST at 10%. How a point-of-sale STC discount sits against GST depends on how the certificates are assigned: check with your accountant. Checked 21 October 2026.

Solar Base keeps every job on one record, from the first enquiry to the meter alteration, and does the portal work for you. See how it works

Margin is not markup

Adding 25% to cost gives a 20% margin, not 25%. Pricing from the margin you want, cost ÷ (1 − margin), keeps the profit you planned once discounts and variations start eating into the job.

Price per watt is the number customers compare quotes on, so it is worth knowing before and after the STC discount, and before the battery muddies it.

Price = cost ÷ (1 − margin)

Worked example

Panels, inverter, racking$7,210
Labour and overheads$1,640
Cost$8,850
At a 25% margin$11,800 ex GST, $0.89/W

Questions installers ask

Should a battery go into the price per watt?

Price per watt only says something about the panels. Compare a battery on its price per usable kWh instead.

Where do the STCs come from?

Work them out with the STC calculator and bring the count across.